| Eksekutor | Tanggal | Proyek | Tugas | Status | Durasi |
|---|---|---|---|---|---|
| Fikri | 20 Oct 2025 | PMS | QA Test | In Progress | 1 Jam |
| Abim | 20 Oct 2025 | PMS | QA Test | In Progress | 1 Jam |
| Fikri | 17 Oct 2025 | PMS & ODOO | QA Test | In Progress | 1 Jam |
| Abim | 17 Oct 2025 | PMS & ODOO | QA Test | In Progress | 1 Jam |
| Abim | 16 Oct 2025 | PMS | Permohonan Permit on Board | Done | 1 Jam |
| Abim | 15 Oct 2025 | PMS & ODOO | QA Test | In Progress | 8 Jam |
| Fikri | 15 Oct 2025 | PMS & ODOO | QA Test | In Progress | 8 Jam |
| Abim | 14 Oct 2025 | PMS & ODOO | QA Test | In Progress | 8 Jam |
| Fikri | 14 Oct 2025 | PMS & ODOO | QA Test | In Progress | 8 Jam |
| Abim | 13 Oct 2025 | PMS & ODOO | QA Test | In Progress | 8 Jam |
| Aksi |
|---|
Eksekutor: Fikri
Durasi: 1
Eksekutor: Abim
Durasi: 1
Eksekutor: Fikri
Durasi: 1
Eksekutor: Abim
Durasi: 1
Eksekutor: Abim
Durasi: 1
Eksekutor: Abim
Durasi: 8
Eksekutor: Fikri
Durasi: 8
Eksekutor: Abim
Durasi: 8
Eksekutor: Fikri
Durasi: 8
Eksekutor: Abim
Durasi: 8